Project facts
- Location — Detail: Kakheti: Telavi; Dvarpatiosani area (south-west of Telavi); Turdo river valley towards Chiloboni and Tsklebi
- Installation contractor — Detail: Installed by a contractor; chamber equipment supplied by GON
- Equipment — Detail: Gate valves, dismantling joints, battery-powered electromagnetic flow meters (sizes and specification: ask our sales team)
- Date of works — Detail: Completed in 2026
- Status — Detail: Completed
- Evidence — Detail: GON project map layer (three pin groups); no geotagged photos yet
The requirement
A town or village network needs to know how much water enters it. Without a meter at the source or tank outlet, the supplier cannot compare inflow with what consumers actually use, and cannot tell a leak from normal demand. A bulk meter at each entry point gives that baseline. That is why the Telavi cluster sits alongside our other bulk metering work: see the nationwide overview.
What a standard chamber contains
We have documented the standard chamber at Manglisi and Tetritskaro. In order along the pipe:
- Gate valve (upstream isolation)
- Dismantling joint, so the meter can be removed without cutting the line
- Battery-powered electromagnetic flow meter
- Gate valve (downstream isolation)
The assembly sits in a concrete chamber with a drain sump and a ladder. Where PE pipe meets the steel spool through the chamber wall, a PE flange adapter makes the transition, and the outside is waterproofed with bitumen. This is the standard GON chamber configuration.
Three groups of points
- Telavi: points on the town's own supply.
- Dvarpatiosani area: points south-west of Telavi.
- Turdo river valley: points along the valley towards Chiloboni and Tsklebi.
Chambers in valleys and near rivers must stay accessible and as dry as possible, which is why the sump, ladder and waterproofing are part of the standard design rather than options.
Result
The Telavi points are completed and show that bulk metering in Kakheti extends beyond the village rollout described in our Kakheti case study. This page will be updated with the final scope and site photos.
Local context
Other public programmes in Telavi are separate from GON's work. The ADB-financed Telavi Water Supply System Improvement project, with UWSCG as borrower, added boreholes, reservoirs, a rehabilitated distribution network and customer metering, and was complete in June 2023 (ADB). Before it, only 18% of residents had 24-hour supply (PMCG). In 2026 UWSCG invited expressions of interest for detailed design of sewerage in Telavi and Kurdghelauri, and water and sewerage in Vardisubani and Shalauri (water.gov.ge).
Products used
- Water metering: electromagnetic flow meters
- Valves: ductile iron gate valves
- Fittings: dismantling joints, PE flange adapters
- Pipes: PE and steel
Related reading
- Bulk flow meters: electromagnetic, ultrasonic, Woltmann
- Remote-read water meters
- Dmanisi: 19 villages, PE100 pipe and meter boxes
FAQ
Where exactly are the Telavi metering points? Our map shows pins in Telavi, the Dvarpatiosani area south-west of the town and the Turdo valley towards Chiloboni and Tsklebi. For exact sites, ask our sales team.
Why use a dismantling joint next to the flow meter? It lets crews remove the meter for calibration or replacement without cutting the pipe.
Can the meters be read remotely? Battery-powered electromagnetic meters can be fitted for remote reading; ask our sales team which option suits your project.
Can GON supply the same chamber equipment for our tender? Yes. Send the bill of quantities and we will price the valves, joints and meters.
Need the exact sizes and specification? Ask our sales team
Pipe sizes (DN), meter specification and quantities depend on each project. Contact GON's sales team at gon.ge/contact or call +995 595 818 800. Send your bill of quantities (BOQ) and we will respond with a supply proposal.